Update, 18th November 2026: Barcelona City Council's urban planning commission approved the €5.73 million increase for the Rambla renovation on Wednesday, citing more extensive archaeological work and additional anti-terrorist bollards, among other factors, according to El Periódico. The vote passed with support from Comuns and ERC, while Junts and Vox abstained and PP opposed, amid opposition criticism over cost management. The city's manager of mobility, infrastructure and works, Ricard Font, outlined five reasons for the adjustment, including expanded archaeological findings, a security audit, sewage studies, waterproofing at metro stations and heritage improvements.

Barcelona City Council is due to vote on Wednesday 18th November on a €5.73 million increase to two contracts for the renovation of La Rambla, the city’s central promenade. A majority of council groups are expected to support the change, according to reporting by La Vanguardia.

The vote affects a project that residents, businesses and visitors will continue to encounter on La Rambla until February 2027, when the work is scheduled to finish. Construction is taking place at weekends as well as during the week, the newspaper reports.

The proposal will be considered by a committee that brings together government and opposition items normally dealt with by four separate council committees. La Vanguardia reports that the People’s Party, or PP, will vote against the increase.

The change concerns the redevelopment project for the promenade and its adjoining roads and pavements. It has not yet been approved.


Four areas behind the additional costs

According to La Vanguardia, the proposed increase is justified by additional work in four areas:

  • Support for archaeological interventions.
  • Stronger security in public space.
  • Rehabilitation of the sewer network.
  • Conservation and improvement of existing features.

Mayor Jaume Collboni’s administration has shortened a construction timetable that had initially been expected to last nearly six years, the newspaper reports.

The council’s La Rambla works page says carrying out construction across the full stretch has reduced the time needed compared with working in successive sections. The stretch runs from Carrer Portal de Santa Madrona to Plaça de Catalunya.

The renovation is intended to be ready for an opening celebration on 13th and 14th February 2027, according to La Vanguardia. Municipal elections are scheduled for 23rd May 2027.


What the council’s existing budget covers

In its 2025–2028 action plan for La Rambla and its surroundings, Barcelona City Council puts the estimated cost of the new promenade at €55.6 million. The plan says construction began in June 2024 and is expected to finish in February 2027.

That estimate is listed in the existing action plan; the proposed €5.73 million contract increase is due to be considered separately at Wednesday’s committee meeting.

The plan says the project covers the central promenade and the roads and pavements on both the Raval and Gòtic sides. These are the two neighbourhoods adjoining La Rambla.

As well as changing the physical layout, the council says its project aims to improve accessibility and connections between Raval and Gòtic, support local life and economic activity, and promote sustainable tourism.

For residents and businesses checking the extent of the works, the council’s La Rambla works page identifies the route covered by the renovation.


Sources: La Vanguardia, Ajuntament de Barcelona.