Barcelona Airport has completed the construction phase that required it to operate with a single runway, airport operator Aena said on Thursday 26th November. The work finished hours ahead of schedule, allowing the airport to return to its usual runway configuration.

For passengers using Josep Tarradellas Barcelona-El Prat Airport, the phase with the greatest planned effect on operations has ended. Work continues on a new rapid exit from runway 02/20, but Aena says the remaining phases do not affect operational capacity.

Aena announced the completion in a statement reported by Europa Press. The public airport operator said the new exit is not yet available for use and that the project will not increase the airport’s declared capacity.


Noise and runway restrictions

Aena said its planning took account of the airport’s historical weather data. During the single-runway period, it said, there was no need to use an easterly runway configuration, minimising the noise impact on surrounding municipalities.

In its construction notice published on 18th September, Aena had identified 16th to 26th November as the period of greatest disruption, when the airport would operate with one runway.

The operator said it had coordinated the work in advance with airlines and the bodies responsible for allocating flight slots, so schedules could be adapted to the temporary reduction in capacity.

An earlier Aena announcement on 13th March had planned for approximately 22 arrivals and 22 departures per hour during the main phase. It also said non-preferred take-offs would not be permitted during that phase.


What the new exit will do

The €3.1 million project will connect runway 02/20, the airport’s cross runway, to taxiway T4. Aena says the rapid exit will allow aircraft to leave the runway sooner after landing.

The construction includes:

  • New pavement for the exit.
  • Drainage and airfield lighting systems.
  • The necessary electricity supply.

Aena expects the exit to reduce waiting in the air and on the ground, as well as manoeuvres and taxiing times. It says those changes will help reduce fuel consumption, emissions and noise, while improving punctuality.

The September notice gives a planned construction period of 12 and a half months. It also says the exit will make runway use more efficient and help with certain changes of runway configuration, including the preferred arrangement at night.


Sources: aena.es.