# Barcelona to Reinforce Power Grid with New Substations
- URL: https://barna.news/barcelona-to-reinforce-power-grid-with/
- Published: 2026-11-27T08:49:36.000Z
- Updated: 2026-11-27T08:50:36.000Z
- Description: Endesa plans major upgrades to Barcelona’s electrical infrastructure to meet rising energy demands.
- Author: Barna.News News Desk
- Tags: Urban Development

## Barcelona’s Electrical Network Undergoing Major Expansion

The electricity supply in Barcelona relies on a complex, interconnected system that spans the city and surrounding municipalities, including Badalona, Santa Coloma de Gramenet, Sant Adrià de Besòs, and L'Hospitalet de Llobregat. High-tension lines, substations, medium-tension networks, and transformation centres work together to deliver power across administrative boundaries, functioning like an electrical highway system. Transmission lines operating at 220 kV and 400 kV carry large volumes of energy into the region, while substations act as interchanges, reducing voltage and directing power into medium-tension lines. These then feed into transformation centres that deliver usable electricity to homes, businesses, public services, and industries.

## Addressing Rising Energy Demand

Barcelona’s growing energy needs, driven by electric mobility, urban expansion, and economic activity, are prompting a significant reinforcement of the city’s grid. Endesa’s planned actions go beyond simple facility renovations, focusing heavily on increasing network capacity, flexibility, and resilience through strategic new connections and infrastructure. Having multiple routes for electricity flow is crucial during maintenance or outages, allowing for rerouting and continued supply. A key part of this strategy involves creating new circuits and modernising existing facilities across the metropolitan area.

## New 110 kV Circuit Between Sant Andreu and Collblanc

One of the flagship projects is the construction of a new double 110 kV circuit linking Sant Andreu and Collblanc. This will strengthen the connection between two critical nodes in the grid, increase overall capacity, and allow for better redistribution of energy flows when needed.

## Major Upgrades Along the Besòs Axis

The Besòs corridor is a focal point for infrastructure investment. A new underground 110 kV link will connect the Mata and Besòs substations, complemented by the modernisation of both facilities’ electrical parks. The upgrades will introduce more flexible technology to manage the network under varying conditions. Another key project involves a new 110 kV circuit connecting Besòs, Sant Martí, and Cerdanyola, enhancing metropolitan-level distribution resilience. In Sant Martí, the existing 110/25 kV substation will also be modernised to meet current demands.

## New Provençals Substation in Poblenou

Poblenou will gain a new distribution hub with the construction of the Provençals substation. Operating at 110/25 kV and equipped with three 40 MVA transformers, it will serve as a new node in Barcelona’s grid, reinforcing the Besòs-Provençals-Sant Andreu corridor. Its commissioning will not only add a new distribution point but also reflect a broader strategy: adapting to the city’s evolution requires not just upgrading old infrastructure, but also building new nodes where demand is growing.

## Wider Modernisation Programme

Beyond new lines and substations, Endesa will upgrade major transformation points across the city. At the Besòs substation, one transformer will be renovated. In Santa Coloma de Gramenet, a new high-tension line will be built and three transformers modernised to increase capacity. Other facilities slated for modernisation include Provençals, Sant Martí, Valldonzella, L'Hospitalet, Penitents, Santa Coloma, Mata, Sant Andreu, and Collblanc. Interventions will vary, from replacing transformers to updating switching and control equipment, and will make installations more compact and efficient. These coordinated efforts aim to ensure Barcelona’s power grid can handle increasing demand, offer flexible routing options, and quickly adapt during incidents or maintenance, securing reliable electricity supply for the future.

---

*Sources:* [*El Periódico*](https://www.elperiodico.com/es/barcelona/20261127/grandes-infraestructuras-electricas-barcelona-136797374?ref=barna.news)*.*

---

### Related on Barna.News

- [Besòs Consortium Approves €87M for Tres Xemeneies Revamp](https://barna.news/besos-consortium-approves-87m-for-tres/)
- [Festa Major de Sant Andreu 2026: Full Programme Released](https://barna.news/festa-major-de-sant-andreu-2026-full/)
- [Festa Major de Sant Andreu Boosts Accessibility for All](https://barna.news/festa-major-de-sant-andreu-boosts/)
- [Business Leaders Revive Plan to Extend Diagonal to Llobregat](https://barna.news/business-leaders-revive-plan-to-extend/)